Thursday, April 12, 2012

Project Finance


Investment in a constructed facility represents a cost in the short term that returns benefits only over the long term use of the facility. Thus, costs occur earlier than the benefits, and owners of facilities must obtain the capital resources to finance the costs of construction. A project cannot proceed without adequate financing, and the cost of providing adequate financing can be quite large. For these reasons, attention to project finance is an important aspect of project management. Finance is also a concern to the other organizations involved in a project such as the general contractor and material suppliers. Unless an owner immediately and completely covers the costs incurred by each participant, these organizations face financing problems of their own.
At a more general level, project finance is only one aspect of the general problem of corporate finance. If numerous projects are considered and financed together, then the net cash flow requirements constitutes the corporate financing problem for capital investment. Whether project finance is performed at the project or at the corporate level does not alter the basic financing problem.
In essence, the project finance problem is to obtain funds to bridge the time between making expenditures and obtaining revenues. Based on the conceptual plan, the cost estimate and the construction plan, the cash flow of costs and receipts for a project can be estimated. Normally, this cash flow will involve expenditures in early periods. Covering this negative cash balance in the most beneficial or cost effective fashion is the project finance problem. During planning and design, expenditures of the owner are modest, whereas substantial costs are incurred during construction. Only after the facility is complete do revenues begin. In contrast, a contractor would receive periodic payments from the owner as construction proceeds. However, a contractor also may have a negative cash balance due to delays in payment and retainage of profits or cost reimbursements on the part of the owner.
Plans considered by owners for facility financing typically have both long and short term aspects. In the long term, sources of revenue include sales, grants, and tax revenues. Borrowed funds must be eventually paid back from these other sources. In the short term, a wider variety of financing options exist, including borrowing, grants, corporate investment funds, payment delays and others. Many of these financing options involve the participation of third parties such as banks or bond underwriters. For private facilities such as office buildings, it is customary to have completely different financing arrangements during the construction period and during the period of facility use. During the latter period, mortgage or loan funds can be secured by the value of the facility itself. Thus, different arrangements of financing options and participants are possible at different stages of a project, so the practice of financial planning is often complicated.
On the other hand, the options for borrowing by contractors to bridge their expenditures and receipts during construction are relatively limited. For small or medium size projects, overdrafts from bank accounts are the most common form of construction financing. Usually, a maximum limit is imposed on an overdraft account by the bank on the basis of expected expenditures and receipts for the duration of construction. Contractors who are engaged in large projects often own substantial assets and can make use of other forms of financing which have lower interest charges than overdrafting.
In recent years, there has been growing interest in design-build-operate projects in which owners prescribe functional requirements and a contractor handles financing. Contractors are repaid over a period of time from project revenues or government payments. Eventually, ownership of the facilities is transferred to a government entity.

Wednesday, April 11, 2012

Project Management Guide


If you come across the big question of what should project managers do to be able to make a job accomplished easily, then this article will be very helpful to you. The project manager is the one who carries the biggest responsibility in a construction firm. He is the one who holds the success of a company. Once the project is accomplished and the tasks are executed properly, the credit is due to the project manager because he is the one who handles everything in the company.
There are project managers who are inexperienced, it is very risky for a company to have inexperienced project managers in the company. If you would like to have a successful business, it will be best for you to know that there are important things you need to keep in mind:
1. The need to look for help if you have inexperienced project managers is very vital. If you know that you still lack experience to get the job done easily, there is someone in the company that can help you with your training needs. Usually, a company allows newly hired project managers to go through training from someone who is well verse in the field.
2. It is important for you to equip yourself with software to be able to get the job done easily. A lot of companies’ today especially big firms know the importance of software that is why most of them include software for a tool whenever they need to work more efficiently.
3. Learning the details of every project is also important and as a newbie in the industry, it will be best for you to know that taking care of proposals and other things as well will be very helpful to you.
As a project manager, there are lots of responsibilities on your shoulders so you need to be equipped with all the right information so that you will never miss a thing.

Managing Your Website Development ?eight Easy Steps to Project Management

Managing your website development need not cause you sleepless nights providing you learn the secrets of successful project management. Perform the best practices in project management and give your project the best chance of success.


Define objectives-
Objectives guide everyone on the project to your final goals. Are your objectives to sell your product online, to provide customer support, to promote investor relations? Carefully decide and clearly document your objectives.
Decide the critical success factors ?the things at the end of the project which tell you if you’ve been successful. Make them measurable so you know if you’ve achieved them. For example, the website development should result in an increase in online sales of 25% by year end.
Stakeholder analysis-
A stakeholder is someone with an interest in your project’s success (or failure). Decide who they are and whether they support your project. Perform stakeholder analysis by classifying them (high or low) according to how motivated they are in helping (or blocking) your project and how influential (high or low) they are.
Highly influential and supportive people are your allies. Gain their support whenever you can. Aim to reduce the influence of people who are both highly influential and against your project as these people could act to damage your project.
During your stakeholder analysis, draw up strategies for dealing with each group of stakeholders.
Define deliverables-
Deliverables are tangible things produced during the project. Talk with key stakeholders to help define deliverables. Will your website design include web page layouts and sitemap for use by the programming team? What is the content for each page? Write all this down.
Key stakeholders must review and agree the deliverables accurately reflect what they expect to be delivered.
Project planning-
Define how you will arrive at your objectives. This involves planning how many people, resources and budget are required. If delivering this in house, decide what activities are required to produce each deliverable.
For example, you might decide a web designer will develop page layouts and navigation diagrams. You might decide the marketing team will supply all product details and photographs. You might decide the finance manager will set up merchant and payment gateway accounts to enable e-commerce transactions via your website. If outsourcing work, specify exactly what the sub-contractor should deliver.
Estimate the time and effort required for each activity and decide realistic schedules and budget. Ensure key stakeholders review and agree the plan and budget.
Communication planning-
Hold a kick off meeting with the team and explain the plan. Ensure everyone knows exactly what the schedule is, and what is expected of them.
For example, the web designer needs to know that he is to produce page layouts and navigation diagrams based upon the marketing manager’s requirements. He needs to know his expected start and end times.
Share your project communication plan with the team. This should include details of report templates, frequency of reporting and meetings, and details of how conflicts between teams and their members will be resolved.
Project tracking-
Constant monitoring of variations between actual and planned cost, schedule and scope is required. Report variations to key stakeholders and take corrective actions if variations occur. To get a project back on track you will need to juggle cost, scope and schedule.
Suppose your programmer hits technical problems which threaten to delay the project. You might recover time by re-organising or shortening remaining tasks. If that’s not possible, you might consider increasing the budget to employ an additional programmer, or consider reducing the scope in other areas.
Be aware that any adjustments you make to the plan might affect the quality of deliverables. If you need to increase the budget, seek approval from the project sponsor.
Change management-
Once started, all projects change. Decide a simple change strategy with key stakeholders. This could be a committee which decides to accept or reject changes which comprises of you and one or more key stakeholders.
Assess the impact of each change on scope, cost and schedule. Decide to accept or reject the change. Be aware that the more changes you accept the less chance you have of completing the project on time and within budget unless you reduce scope in other areas.
Suppose the marketing manager wants to add a popup window to display full size photographs of products. Assess the impact of this change. You might need to remove some remaining tasks to include this change and stay within budget. Or, it might be impossible to include the change without increasing the budget or schedule.
Don’t blindly accept changes without assessing the impact or your project will overrun.
Risk management
Risks are events which can adversely affect the success of the project. Identify risks to a project early. Decide if each risk is likely or unlikely to occur. Decide if its impact on the project is high or low.
Risks that are likely to occur and have high impact are the severest risks. High impact but unlikely risks, or low impact but likely risks pose a medium threat. Unlikely and low impact risks pose the least threat.
Create a mitigation plan of the actions necessary to reduce the impact if the risk occurs. Start with the severest risks first, then deal with the medium risks. Regularly review risks. Add new ones if they occur.
Suppose the marketing manager cannot decide what he wants from the website. Without knowing what the marketing manager wants, the team cannot deliver a website to meet his expectations. You assess this risk as highly likely to occur and having high impact. Your mitigation plan might be that the web designer develops page layouts to be reviewed by the manager early in the project.
Summary
Performing best practices in project management will give your website development project the best chance of success.

Monday, April 9, 2012

Concrete Mix Design Secrets


In order to make a concrete mix design that works, you should master all the concrete theories in combination with experiences of concreting at work. Here is some important things you need to know when design concrete mixes.

A. What do you need to know before designing concrete?

1. What are the strength requirements?
- Compressive (on cube or cylinder specimen) strength
- Flexural strength
- Tensile strength
2. What is the placing method? By pump or direct pouring?
3. How far is the job site from the batching plant?
4. What is the structure for casting? Pavement, foundation, elevated slab, etc.
5. What are the projects specification?
- Maximum or minimum cement contents
- Maximum water/cement ratio
- Slump or consistency limit
- Minimum Strength requirement @28 days
- Material specifications (what is the maximum size of aggregate?)
6. Latest testing results of materials is needed in the preliminary selection of materials and design calculation

B. What are Design Precautions and Things to Remember when design concrete mixes?

1. Increasing the sand/total aggregate ratio, increases the water requirement at the same consistency.
2. Increasing the water/cement ratio decreases the strength of concrete at the same cement content.
3. Remember that adding 5 liters of water per cubic meter increases the slump by 2.5cm.
4. Remember that adding 5 liters of water per cubic meter decreases strength by approximately 4%.
5. Always follow recommended admixture dosage.
6. Always have “control” when performing trial mixes, always perform trial mixes with another mix using the same materials. This data can be useful in diagnostics if a problem occurs.
7. Always adjust batching quantities to the actual moisture condition of the aggregates.
8. Volume tolerance for 1m3 concrete is 1 ± 0.2m3.
9. Range of normal weight concrete is from 2,200 kg/m3 to 2,400 kg/m3

What You Need To Know About Being A Business Coach


If a new profession is in your future and you enjoy the areas of business and personal development, you might be an excellent candidate to become a business coach. This is somebody who helps many people and companies identify and achieve their goals. This is an incredibly fulfilling career, in that you’re helping individuals become more productive and successful and the more experience you get, the more you can charge for your services. Read on to discover a few of the advantages to being a business coach.
Business coaches have a generous assortment of potential clients. Men and women searching for employment and entrepreneurs of all kinds may pay you to assist their efforts in a variety of areas. You can do this in many locations but, naturally, you must consider how well the economy is doing in a particular area. You may even coach people over the Internet or by phone so you aren’t required to live in the same location they do. On the other hand, a business might want to hire you for a specified period of time to help train or motivate some of their workers. So as a business coach, you have numerous possibilities available, whether you want to work with clients one-on-one, long distance or give presentations to organizations.
Before you make the decision to take up a career as a business coach, there are a couple of questions you should consider. Are you a people person? Is teaching one of your inherent talents? Though it’s possible to learn most of the techniques and marketing skills you need to become an excellent coach, you also need a certain type of personality. As you well know, one of your main tasks is to provide motivation for others. It’s also beneficial to get excited about your job so that people will want to improve themselves as well. Moreover, it’s not a bad idea if it makes you feel great to help other people learn to do new and different things. If this might be you, coaching could be your best career option.
If you’re looking at a career in business coaching, you should evaluate your skills and determine if there any additional ones you need to obtain. For instance, you may have just the right amount of business experience to qualify you to teach others. Yet, if you’re not comfortable speaking in front of people, or your communication skills are lacking in any way, this is something you must work on. If you aren’t updated on the latest software used by businesses, you’ll need to get up to speed on this. Once you begin coaching, you want to be sure that you have made every required preparation.
There is a serious demand for business coaches today, so this is a profession worth considering if you like working with and teaching people. It is possible to take several paths on the road to realizing your career as a coach and no special certification is needed. Nevertheless, you can most certainly find schools who will provide certification if you believe you need it.

Construction Risks Analysis and Management


Analyze and manage risks in construction is very important for project management. This help to avoid or limit risks in construction projects.
The construction risks can be broadly grouped under the following categories:
. Technical Risks
* Incomplete design.
* Inadequate site investigation.
* Uncertainty over the source and availability of materials.
* Appropriateness of specifications.
. Logistical Risks
* Availability of resources – particularly construction equipments, spare parts, fuel and labor.
* Availability of sufficient transportation facilities.
Construction Risks
* Uncertain productivity of resources.
* Weather and seasonal implications.
* Industrial relations problems.
. Financial Risks
* Inflation.
* Availability and fluctuation in foreign exchange.
* Delay in Payment.
* Repatriation of funds.
* Local taxes.
. Political Risks
* Constraints on the availability and employment of expatriate staff.
* Customs and import restrictions and procedures.
* Difficulties in disposing of plant and equipment.
* Insistence on use of local firms and agents.

Sunday, April 1, 2012

Total Quality Control in Construction


Quality control in construction typically involves insuring compliance with minimum standards of material and workmanship in order to insure the performance of the facility according to the design. These minimum standards are contained in the specifications described in the previous section. For the purpose of insuring compliance, random samples and statistical methods are commonly used as the basis for accepting or rejecting work completed and batches of materials. Rejection of a batch is based on non-conformance or violation of the relevant design specifications. Procedures for this quality control practice are described in the following sections.
An implicit assumption in these traditional quality control practices is the notion of an acceptable quality level which is a allowable fraction of defective items. Materials obtained from suppliers or work performed by an organization is inspected and passed as acceptable if the estimated defective percentage is within the acceptable quality level. Problems with materials or goods are corrected after delivery of the product.
In contrast to this traditional approach of quality control is the goal of total quality control. In this system, no defective items are allowed anywhere in the construction process. While the zero defects goal can never be permanently obtained, it provides a goal so that an organization is never satisfied with its quality control program even if defects are reduced by substantial amounts year after year. This concept and approach to quality control was first developed in manufacturing firms in Japan and Europe, but has since spread to many construction companies. The best known formal certification for quality improvement is the International Organization for Standardization’s ISO 9000 standard. ISO 9000 emphasizes good documentation, quality goals and a series of cycles of planning, implementation and review.
Total quality control is a commitment to quality expressed in all parts of an organization and typically involves many elements. Design reviews to insure safe and effective construction procedures are a major element. Other elements include extensive training for personnel, shifting the responsibility for detecting defects from quality control inspectors to workers, and continually maintaining equipment. Worker involvement in improved quality control is often formalized in quality circles in which groups of workers meet regularly to make suggestions for quality improvement. Material suppliers are also required to insure zero defects in delivered goods. Initally, all materials from a supplier are inspected and batches of goods with any defective items are returned. Suppliers with good records can be certified and not subject to complete inspection subsequently.
The traditional microeconomic view of quality control is that there is an “optimum” proportion of defective items. Trying to achieve greater quality than this optimum would substantially increase costs of inspection and reduce worker productivity. However, many companies have found that commitment to total quality control has substantial economic benefits that had been unappreciated in traditional approaches. Expenses associated with inventory, rework, scrap and warranties were reduced. Worker enthusiasm and commitment improved. Customers often appreciated higher quality work and would pay a premium for good quality. As a result, improved quality control became a competitive advantage.
Of course, total quality control is difficult to apply, particular in construction. The unique nature of each facility, the variability in the workforce, the multitude of subcontractors and the cost of making necessary investments in education and procedures make programs of total quality control in construction difficult. Nevertheless, a commitment to improved quality even without endorsing the goal of zero defects can pay real dividends to organizations.